03-06-20 Everyone have been working hard and fast to complete the approx. 1000 m² of freezer storage for Tican within the time frame, which was just 2 weeks.

In addition to supplying and installing 200 mm thick PIR panels for the 8 m high warehouse, DC-System will also supply and install mineral wool panels for a master office.